Please find below some of the works currently ongoing with a potential to cause disruption, however the list of works is not exhaustive. Please visit One Network for the most up to date information.
Page contents
- Cadent Gas works - Vicarage Road, Egham
- SGN works - Shalford and Bramley
- Thames water works - Guildford Road
- S278 works - Mindenhurst Deepcut Village Project
- Godstone Road updates
- Shepperton (Studios Road junction) - construction works
Cadent Gas Works - Vicarage Road, Egham
Cadent Gas will be carrying out essential upgrades to the local gas network on Vicarage Road, Egham from the junction with Pooley Green Road to the junction with the High Street. This is being done as part of their long-term programme to replace ageing metal gas mains with modern plastic pipes.
Programme of works:
- Start date: 30 March 2026
- End date: 11 May 2026
- Duration: Approximately 6 weeks
Traffic management:
- Westbound directional road closure on Vicarage Road
- Pooley Green Road will be closed at its junction with Vicarage Road to prevent diverted traffic using this residential road
- Multi-way traffic signals will be in place at the junction with Vicarage Road between 28 March – 4 April 2026
- Advance warning signs will be installed on all approaches
- Traffic management will move along the road as works progress.
Additional information:
- Access for residents and businesses will be maintained where safe to do so.
- Emergency vehicle access will be maintained at all times.
- Some delays are expected due to the directional closure and signal control.
We appreciate that roadworks can be disruptive and thank residents and road users for their patience while these essential improvements are completed. For more information please contact Cadent Gas on their website.
SGN Works - Shalford and Bramley
SGN (Southern Gas Network) are undertaking gas network upgrade works across Shalford and Bramley. These works form part of SGN’s long-term programme to replace ageing metal gas mains with modern plastic pipes, helping to ensure a continued safe and reliable gas supply for local homes and businesses.
The project is scheduled to begin on Monday 23 March and is expected to last approximately 35 weeks, with works being delivered in phases along Chinthurst Lane and the A281 Horsham Road.
Programme of works:
Chinthurst Lane, Shalford
Start: Monday 23 March
Duration: Approximately 10 weeks
Traffic management: Rolling road closure in sections between The Common and around 100m past Poplar Road
- The closure will move along the road as works progress.
- Poplar Road will also need to be closed at its junction with Chinthurst Lane for approximately two weeks when works reach this section.
A281 Horsham Road, Bramley to Shalford
Start: Tuesday 7 April
Duration: Approximately 32 weeks
Traffic management: Temporary traffic lights moving along the route as works progress
Works will run from the junction with Snowdenham Lane/Station Road (Bramley) to just short of Broadford Road (Shalford).
To help manage traffic flow:
- Side roads will be closed one at a time as works pass each junction:
Snowdenham Lane, Links Road and Foxburrow Hill Road - Additional signal heads may be installed at some junctions.
- Manual control of the traffic lights will be in place Monday to Saturday, 7am–7pm to reduce congestion.
- SGN will also be trialling Remotely Operated Signals (REMOS) smart traffic signals, which adjust timings in real time based on traffic levels.
Local elections:
All traffic management will be removed for one day on Thursday 7 May to allow easier access to polling stations during the planned local elections.
Public drop-in session:
Residents will have the opportunity to view plans and ask questions at a public session:
Date: Thursday 5 March
Time: 6:00pm – 7:30pm
Location: Bramley Village Hall, Hall Road, Bramley GU5 0AX
More information:
More information on these works and regular updates are available on the dedicated SGN project webpage.
Thames Water Works - Guildford Road
Thames Water will be carrying out major water network upgrade works on Guildford Road as part of their long-term investment programme to reduce leakage and improve the reliability of water supplies across Thames Valley and London.
Programme of works:
The works will be completed in phases, starting near the junction with Smithwood Common Road and progressing along Guildford Road towards Cranleigh.
To help complete the works more efficiently and reduce overall disruption:
- From February 2026, Thames Water will operate with two site teams working along Guildford Road
- Temporary traffic lights will be in operation during the works
- Emergency vehicle access will be maintained at all times
Working hours
- Monday to Friday: 8am to 5pm
- Saturday: 8am to 1pm
In some instances, it may be necessary to temporarily turn off water supplies. If this is required, affected customers will be contacted directly in advance with further details.
More information:
For enquiries please contact Thames Water directly on 0800 316 980
We will continue to monitor these works and update this page if there are any changes to timings or traffic management.
S278 works- Mindenhurst Deepcut Village Project
Knights Brown in partnership with Skanska, as part of the wider Mindenhurst Deepcut Village project is carrying out this major development works. These will deliver 1,200 new homes, a primary school, nursery, sports pitches and a village pub, bringing new facilities for residents in Deepcut.
Gole Road / Dawney Hill Works
- Vegetation clearance and utility diversions to the east of Dawney Hill.
- Installation of an additional southbound lane on Dawney Hill.
Traffic management
- Road closure for northbound traffic on Dawney Hill from Caterham Close for the duration of the works.
- A signed diversion route will be in place.
- A full road closure will be required in January / February 2026 (20:00–06:00) to complete carriageway resurfacing.
M3 Junction 3 (A322) Works
- Widening of the westbound carriageway to provide an additional lane from Guildford to the M3.
- Construction of a new signalled crossing point, improved drainage, vegetation clearance and localised footpath improvements.
Traffic management
- The A322 will be fully closed overnight (9pm to 6am) in January and February 2026 for resurfacing.
- A signalled diversion route will be in place during this closure.
Programme
- Start date: Monday 13 October 2025
- Duration: Approximately 22 weeks
Additional information
- Weekend working is not currently planned; however, Saturday working may be required in the event of delays.
- Refuse collection will continue throughout the works.
- Access needs and large deliveries can be raised directly with the site team, who will seek to accommodate where possible.
- Project team will be carrying out letter drops to the affected residents of the area and Advance Warning Signs will be in place prior to the works start date.
These works are an important part of supporting the Mindenhurst development and improving transport links at key locations in Surrey.
We will continue to monitor and provide updates as the project progresses.
Further details on the Mindenhurst Deepcut Village project can be found at Homepage - Mindenhurst
For enquiries, please contact Knights Brown.
Godstone sinkhole updates
A25, Godstone currently is closed in both directions due a large sinkhole. SES water, SGN and UK Power Networks are currently working on site.
While the situation is stabilising, it will be treated as an ongoing significant incident, which means all agencies in Surrey working closely to focus on supporting residents and moving to repair and recovery.
We understand the disruption and uncertainty this is causing residents and those traveling near the area. We will continue to update this page as the works continue.
Diversion routes:
The diversion route for the road closure is A25 Oxted Road, A22 Godstone Bypass, Eastbourne Road. This diversion route has also been symbolised to reduce the confusion for the motorists. We are ensuring that parking restrictions are in place on Eastbourne Road from Monday onwards for the end of half term when we expect traffic levels to increase.
Properties in the wider area now have access to water and power as normal and the impacted homes are confined within the cordon. More permanent repairs will be carried out once the site is deemed safe to work in.
Oxted Road ( A25) is expected to be down to 1 set of lights soon as SES Water have completed and replaced the mains valve opposite/ adjacent to Salisbury Road, on the Eastbound side of the A25. The set further up will stay in situ as this is allowing a standpipe to vent the smaller main being used to replace the supply of the larger one in the High Street. Traffic impact on these lights has been minimal as reported after Streetworks officer's visit,
SES Water have confirmed that water had been restored to properties within RH1 and RH9.
More information about these works can be found on SES Water website.
Closure of Bullbeggars Lane and Church Lane:
Due to the traffic on Eastbourne Road, towards the A22 queuing back to Church Lane, Bullbeggars Lane and Church Lane have now been closed.
We will be updating this webpage as and when more information becomes available.
Information on these works can also be found on Update on Godstone sinkhole.
Construction works at the junction of Studios Road, Squire's Bridge and Road New Road
Summary: Shepperton Studios have a history dating back to 1931. They have had extension works ongoing since 2023. The development makes Shepperton Studios the second biggest film studio in the world with a total of 31 purpose-built sound stages alongside additional production accommodation, the whole site covering 1.5 million square feet. The completion of Shepperton is intended to allow incredible new shows, jobs and a boost for the economy.
Duration and Impact: Offline works (construction taking place that requires no traffic management) have been ongoing since 17 June 2024. This offline work is scheduled to take 12 weeks to complete. Traffic management will then be in place after this stage (around mid-September 2024) and will last approximately 24 weeks. This will be done to ensure the safety of road users and all other stakeholders.
Further Information: More information about this project can be found at Shepperton studio's website.