Runnymede roundabout remedial works

What is happening?

Following completion of the Runnymede Roundabout scheme there are some defects that need remedial repairs.

There will be three weeks of daytime off peak works and one week of night-time working.

  • Monday 15 July – Friday 2 August between 9:30am and 3:30pm. A series of lane closures will be in place Monday to Friday only. We will also be carrying out minor works to pavements and grass verges.
  • Monday 22 July between 8pm and 6am. A full closure of the A308 The Glanty from the roundabout to Woodhaw for traffic heading towards Staines only. In addition the U-turn facility will also be closed.
  • Tuesday 23 July – Friday 26 July between 8pm and 6am. A series of lane closures will be put in place to allow repairs to the road surface to be carried out.
  • Monday 29 July – Wednesday 31 July 24 hours. A 24 hour lane closure will be in place on the A30.

These works are being carried out by our contractor Buckingham Group at no extra cost to Surrey County Council.

We would like to apologise for any inconvenience these works cause.