A325 Guildford Road Farnham Scottish and Southern Energy works

Location: A325 Guildford Road, Farnham

Duration: 2 September 2019 to 30 November 2019

Reason for Works

Installation of 574 metres of a new low voltage cabling network to replace the existing faulty network, to carry out the service transfers to residents and businesses and also the street lighting and furniture. This is in order to prevent the constant cable faults and to make the network more efficient for the residents and businesses.

Extents of Works

The works start outside the Farnham Fire Station and end approximately 45 metres east of the junction with Anstey Road.

Traffic Management

  • Phase 1: Road Closure from outside the Territorial Army Centre to Farnham Fire Station (6-8 weeks).
  • Phase 2: Multi-Way Signals at the junction with Forge Close and Guildford Road Trading Estate. (4-5 weeks).

If you have any enquiries about these works please visit the SSEN website.