Skip to main content

A23 Redhill and Horley drainage improvement works

Scheme overview

The A23 Local Enterprise Partnership (LEP) project began in early January 2018 and aims to improve the drainage and resilience of sections of the A23 network following on from the flooding during the winter of 2013/14. This project is being partly funded by the Coast to Capital LEP and the objective is to mitigate the effects of major flooding events in the future. The project is being delivered in several phases some of which include drainage improvements, repairs and carriageway resurfacing.

Some of the benefits of the works include:

  • Improving the overall road safety for vehicles, pedestrians and cyclists
  • Helping to reduce the likelihood of surface water flooding
  • Prolonging the life of the carriageway
  • Helping to deliver economic prosperity in Surrey
  • Improving the road conditions for the new shared pedestrian / cycle path and bus stops.

To find out about the on-going works to construct the new shared pedestrian / cycle path along the A23 please visit our A23 Horley Road, Redhill web page.

Stages of drainage improvement works

Daytime lane closures and temporary traffic lights (9:30am – 4pm):

  • Chequers Roundabout to Crossoak Lane
    23 April 2018 for approximately five weeks
  • Three Arch Road to Woodhatch Road
    During May 2018
  • Grove Hill to Three Arch Road
    During November 2018
  • Woodhatch Road to Lodge Lane
    During December 2018
  • Lodge Lane to Crossoak Lane
    During January 2019

Stages of resurfacing works

Night-time road closures (8pm – 6am):

  • Chequers Roundabout to Crossoak Lane
    During July 2018
  • Three Arch Road to Woodhatch Road
    During August 2018
  • Woodhatch Road to Lodge Lane
    During July 2019

More resurfacing works may be carried out, we will notify you in advance of any additional works.

Please note: adverse weather conditions can delay works so please be aware that these dates and working hours are subject to change; please therefore refer to this page for the most up to date information.

Frequently asked questions

It's a very long road, how are these works going to be carried out?

The works will be carried out in sections and the anticipated dates and locations can be found above.

What hours will you be working?

During the day we will be working off-peak between 9:30am and 4pm. Most work will carried out on weekdays however there may be weekend working. During the night we will be working between 8pm and 6am (weeknights only).

Why are you not working at night or at the weekend?

Night or weekend working significantly increases the overall cost of a project and it will therefore be unaffordable to complete the scheme within the current budget.

Will there be any road closures required?

The resurfacing work will require a road closure at night. The traffic management required for the drainage improvement works will be lane closures and/or temporary traffic lights.

Top