The final list of roads for phase 2 of the Part Night Lighting Programme have now been published below. Lights in these roads will be switched off according to the times in the lists from 6 February 2017.

District / BoroughProvisional implementation dateRevised implementation date
GuildfordDecember 2016Implemented in December 2016
Surrey HeathDecember 2016Implemented in December 2016 
WaverleyDecember 2016Implemented in December 2016 
ElmbridgeJanuary 2017February 2017
Epsom & EwellJanuary 2017February 2017 
Mole ValleyJanuary 2017February 2017 
Reigate and BansteadJanuary 2017February 2017 
RunnymedeFebruary 2017March 2017
SpelthorneFebruary 2017March 2017
TandridgeFebruary 2017March 2017
WokingFebruary 2017March 2017

A list of roads for each district or borough to be included in the part-night lighting programme will be uploaded to this page approximately one month before it begins in that area. 

However, because we are visiting each road to carry out a risk assessment, it is possible a small number of roads in each district or borough may not have been assessed in time to meet the above timelines and will be added to a later phase. 

These will be added to the website approximately one month before part-night lighting begins in those roads. The lists will be updated regularly so please check this page for updates if you are interested in specific roads.

Phase 1

The following are the finalised lists of roads that will be included in phase 1 of the part-night lighting programme, from 1 December 2016. 

The following are the finalised lists of roads that will be included in phase 1 of the part-night lighting programme from 8 December 2016. 

Phase 2

The following are the finalised lists of roads that will be included in phase 2 of the part-night lighting programme, from 06 February 2016.

Phase 3

The following are provisional lists of roads that will be included in phase 3 of the part-night lighting programme.