Minerals and Waste Local Plan

Timetable

Following changes to the Government's local plan system in March 2026, work on the old-style Minerals and Waste Local Plan (MWLP) has stopped and a new-style Minerals and Waste Local Plan is being prepared.

Surrey County Council is starting this work, with responsibility transferring to East Surrey Council and West Surrey Council from 1 April 2027.

Surrey County Council is required to maintain an up-to-date timetable for the preparation of the new-style Minerals and Waste Local Plan.

Surrey County Council's timetable

6 August 2026

  • Publication of Notice of Intention to Commence
  • Publication of Notice of Withdrawal
  • Publication of MWLP timetable

Publication of the notices begins a 4-month notice period so that stakeholders are aware plan-making is beginning. Timetable must be kept up-to-date and set out anticipated and actual dates for key plan-making stages.

Status: Complete

17 December 2026

Scoping Consultation begins: Inviting feedback from stakeholders about how to engage with them and what the MWLP should contain.

Status: Current

29 January 2027

Scoping Consultation ends: Inviting feedback from stakeholders about how to engage with them and what the MWLP should contain.

Status: Not yet begun

19 March 2027

Gateway 1: Self-Assessment of Readiness: Publication of document explaining how SCC has got ready for plan-making. Marks formal commencement of 30-month preparation period.

Status: Not yet begun

East Surrey and West Surrey councils' timetable

3 September 2027

Consultation about MWLP content and evidence begins: Inviting stakeholder feedback about proposed MWLP content and evidence, including draft vision.

15 October 2027

Consultation about MWLP content and evidence ends: Inviting stakeholder feedback about proposed MWLP content and evidence, including draft vision.

3 December 2027

Gateway 2: Planning Inspectorate: Seeking observations and advice from the Planning Inspectorate to support early resolution of potential soundness issues and progress towards requirements prescribed by the Town and Country Planning (Local Planning) (England) Regulations 2026 (2026 regulations).

1 April 2028

Consultation about the draft MWLP begins: Inviting stakeholder feedback about the draft MWLP and its supporting documents.

2 June 2028

Consultation about the draft MWLP ends: Inviting stakeholder feedback about the draft MWLP and its supporting documents.

1 September 2028

Gateway 3 testing: Testing if the draft MWLP has met the ‘prescribed requirements’ set out by the 2026 regulations and can proceed to examination in public.

1 November 2028

MWLP submitted for examination: MWLP submitted to the Secretary of State for examination.

April to July 2029

Examination in public Examination of the MWLP against the tests of soundness set out in the National Planning Policy Framework.

21 September 2029

Adoption: Adoption of MWLP by East and West Surrey Councils. Publication of MWLP and Adoption Statement.


PDFs and CSV files

PDFs

PDF copies of the timetable can be found on our Commonplace consultation website.

CSV files

You can also download the following datasets as CSV files, which can be opened in most spreadsheet applications, such as Microsoft Excel:

  • Local Plan Dataset: provides information about existing and emerging minerals and waste planning documents, including links to the relevant documents.
  • Local Plan Timetable Dataset: provides a CSV version of the Local Plan Timetable.
  • Schedule of amendments to the Local Plan Timetable: lists any changes made to the timetable and explains the reasons for those changes.

Files available to download

  • Local Plan Timetable Dataset
    This spreadsheet contains the expected milestones and stages the Minerals and Waste Local Plan must pass through in order to be adopted.
  • Local Plan Dataset
    This spreadsheet contains the existing and emerging minerals and waste development framework, with the expected date of adoption included
  • Schedule of amendments
    This spreadsheet contains a list of amendments to the local plan timetable, with the date of the amendment and the reason it was made.


Did you find this information helpful?

Rating Did you find the information helpful?

We aren't able to reply to individual comments, so please don't include any personal details.